Navoi Thermal Power Plant Modernization

Project Details

The project was carried out at the combined cycle heat and power plant site with a nominal capacity of 450 MW electrical output and 200 Gcal/hour heat output.
 

Within the scope of the project, 10 tanks belonging to different services were designed and detailed engineering calculations and designs were designed.

 

Detailing is designed to store substances such as demineralized water, fire water, condensate water, clean oil, dirty oil (prismatic tanks), city water
 

In addition, a thickener and a sedimentation tank were designed and detailed projects were prepared. 
 

This international project site was in  Uzbekistan, consultant engineer was in India. So; Project updated in line with comments and revision requests from Uzbekistan, India and Turkey, the project was successfully managed and completed on time.

Client:

Mitsubishi Hitachi Power Systems / Uzbekenergo                                   

Business Area:

Energy Facilities

 

Completion Date:

2019

 

Location:

Navoi / Uzbekistan

 

Scope:

8650 m3 Storage Tanks Capacity  in 1200 m2 Onshore Site Area